Update 4 (Dec. 2024 – Jan. 2025)

  • Writer: Erik Sampson
    Erik Sampson
  • Feb 16
  • 1 min read

Updated: Mar 21






  • Key Project Milestones

    • Slab pour was completed on December 23, 2024, a major milestone achieved ahead of schedule.

    • Site utilities, including storm drainage and catch basin installation, are progressing well and will be completed in January 2025.

    • Structural steel deliveries are set to begin on January 27, 2025 and will continue into early-February.

    • Design updates, including revisions to the kitchen and gym floor box relocations, have been successfully implemented.


  • FF&E Progress

    • Refinements to layouts remain in progress.

    • The IT consultant, ClowdCover, has formally commenced and begun work.

    • Early coordination for the Murphy Stage is underways, and the updated E-Sports proposal is under review by the project team.


  • Key Takeaways

    • Project is on schedule and on budget

    • Project is ready to accept steel and begin to go vertical