Update 4 (Dec. 2024 – Jan. 2025)
- Erik Sampson
- Feb 16
- 1 min read
Updated: Mar 21
Key Project Milestones
Slab pour was completed on December 23, 2024, a major milestone achieved ahead of schedule.
Site utilities, including storm drainage and catch basin installation, are progressing well and will be completed in January 2025.
Structural steel deliveries are set to begin on January 27, 2025 and will continue into early-February.
Design updates, including revisions to the kitchen and gym floor box relocations, have been successfully implemented.
FF&E Progress
Refinements to layouts remain in progress.
The IT consultant, ClowdCover, has formally commenced and begun work.
Early coordination for the Murphy Stage is underways, and the updated E-Sports proposal is under review by the project team.
Key Takeaways
Project is on schedule and on budget
Project is ready to accept steel and begin to go vertical